Sunday, December 7, 2008

The Supreme Court of Administration 18 September 2008 Procedure Ruling

The supreme court decision was a “procedure” ruling. The case is not over and we are studying our next move.
Is it not a traitors statement by Asia LawWorks at the Rayong Court hearing what left the injunction? Read the ending statement from the court below.

“When 2nd Plaint Receiver requested the Administrative court of Rayong Province to cancel the order of Injunction before judgment while the case is still on trial of this court, therefore the First Administrative Court had prior right to cancel the procedure to minimize injurious consequences before judgment.
The order of canceling the Injunction by the First Administrative Court which ordered to cancel the procedure to minimize injurious consequences before judgment by seizing the construction under license No: 162 / 2549, Issued date: November 28, 2549 of 2nd Plaint Receiver, only for the part of building that higher than 14 meters from road surfaces until other order or judgment is given was in agreement with Clause 77 of the Regulations of General Meeting of Supreme Court of Administration governing the Administrative Enquiry Procedures of B.E. 2543 together with Phrase 1 of Article 262 of the Civil Code.

“The claim of 8 Plaintiffs in the Appeal stated that the measurement starting point to find the distance of 200 meters to be in accord with Clause 3 of the Ministerial Regulations of Issue 8 ( B.E. 2519) which stipulated following the Construction Control Act of B.E> 2479 and amended by the Ministerial Regulations of Issue 9 ( B.E. 2521) which stipulated following the Construction Control Act of B.E> 2479 IS AT High Tide line along the Coast Line NOT at the distance of 100 meters from the MSL along Coast Line OUTWARD to the sea however, is the issue concerning tenor of the case which needed to be considered after. The Appeal of 8 Plaint Receivers which stated that the cancellation of Injunction order given by the First Administrative Court was done without enough ground is not reasonable to be taken to proceed.
Therefore the court stands the same order to be in agreement with the order given by the First Administrative Court.

_Signed_ : Assigned Judicial
Mr. Worapot Wisrutpitch
Judicial of the Supreme Court of Administration”

Now compare Issue 9 update with the original Issue 8:

Ministerial Regulation
Issue 9 (B.E. 2521)
Issued under the Building Construction Control Act
B.E. 2479
By the virtue of the Section 15 of the Building Construction Control Act B.E. 2479, the Ministry of Interior issued the following Ministerial Regulations:

1. No. 1 of the Ministerial Regulation No. 8 (B.E. 2519) issued under the Building Construction Control Act B.E. 2479 is to be amended by the followings statement:

“No. 1. This Ministerial Regulation applies within the boundary line of the map. Annexed to the Royal Decree Promulgating the Building Construction Control Act B.E. 2479 in the regions of Tambol Bang Lamung, Tambol Nhong Plalai, Tambol Na Khua and Tambol Nhong Prue of Amphur Bang Lamung of Chonburi Province B.E. 2520”

2. No. 3 of the Ministerial Regulation No. 8 (B.E. 2519) issued under the Building Construction Control Act B.E. 2479 is to be amended by the following statement:

“No 3. To specify the area within the 200 meters measurement from the construction control line see the map. Annexed to the Royal Decree Promulgating the Building Construction Control Act B.E. 2479 in the regions of Tambol Bang Lamung, Tambol Nhong Plalai, Tambol Na Khua and Tambol Nhong Prue of Amphur Bang Lamung of Chonburi Province B.E. 2521 at the seashore in which the following constructions shall not be built:
Place for keeping and selling fuel

• Building of 14 meters higher than road level.

The Ministerial Regulation is hereby given on the date of twenty-third of November B.E. 2521 (1978).

General Lek Naewmalee

Minister of Interior
(Mr. Somchai Leelaprapaporn)
Civil Engineer Grade 7

Note: The reason issuing this Ministerial Regulation due to the updating of the construction control areas in Tambol Bang Lamung, Tambol Na Khua and Tambol Nhong Prue, by extending the construction restriction areas as appeared in the map annexed to the Royal Decree Promulgating the Building Construction Control Act B.E. 2479 controlling over the regions of Tambol Bang Lamung, Tambol Nhong Plalai, Tambol Na Klua and Tambol Nhong Prue of Amphur Bang Lamung of Chonburi Province B.E. 2521. It is, therefore, appropriate to amend the Ministerial Regulation No. 8 (B.E. 2519) issued under the Building Construction Control Act B.E. 2479 governing restriction of the construction of some kinds of building within the controlling areas under the aforesaid Royal Decree.

Copy taken from the Government Gazette No. 95 Section 157 dated 31 December 2521 (1978)

Certified correct
(Mr. Yuthana Rittisit)
Administrative Officer
Public Utility Section

Ministerial Regulation
Issue 8 (B.E. 2519)
Issued under the Building Construction Control Act B.E. 2479
By the virtue of the Section 15 of the Building Construction Control Act B.E. 2479, the Ministry of Interior issued the following Ministerial Regulations:

This Ministerial Regulation
applies to the boundary line shown in the map annexed to the Royal Decree Promulgating the Building Construction Control Act B.E. 2479 in the regions of Tambol Bang Lamung, Tambol Na Khua and Tambol Nhong Prue of Amphur Bang Lamung of Chonburi Province B.E. 2479.”

2. The land areas under this Ministerial Regulation are restricted from construction of the following buildings:

3. To specify the area within the
100 meters measurement from the construction control line see the map. Annexed to the Royal Decree Promulgating the Building Construction Control Act B.E. 2479 in the regions of Tambol Bang Lamung, Tambol Na Khua and Tambol Nhong Prue of Amphur Bang Lamung of Chonburi Province B.E. 2479 at the seashore in which the following constructions shall not be built:

• Building of 14 meters higher than road level.

The area under Article 3 above, Construction of building, house must be at least 8 meters away from Highway No. 3135.
Building or house construction must be provided with 75% open, and uncovered space of size to the land plot on which the construction is applied for.
This Ministerial Regulation is given on the date of twelfth, June B.E. 2519 (1976)
MRV Seni Pramot
Ministry of Interior

Copy taken from the Government Gazette No. 93 Section 87 dated 29 June 1966.
Note:
The reason issuing this Ministerial Regulation is that further to the Royal Decree Promulgating the Building Construction Control Act B.E. 2479 applying to some areas of Tambol Bang Lamung, Tambol Na Klua and Tambol Nhong Prue of Amphur Bang Lamung of Chonburi Province B.E. 2499, and the aforesaid areas are open public resorts. It is appropriate that the areas shall not be allow to construct some kinds of building considered to disturb good environment and generating any kind of wastes, pollutions. This Ministerial Regulation is, therefore, issued.

Certified correct copy
(Signed) Yuthana Rittisit
Administrative Officer
Public Utility Section
Office of the Secretary

Copy taken and reviewed by : Wallada
(Mr. Somchai Leelaprapaporn)
Civil Engineer Grade 7

Friday, October 17, 2008

The October 17 Supreme Court of Administrative Decision

The Supreme Court chose not to change Rayong Court order which lifted the injunction. Because Rayong Court used a expert witness in making their decision the court chose not to interfere.

We wait for the translation which we will post on this blog.

Thursday, October 9, 2008

On October 17 a Supreme Court decision will be read at Rayon Administrative Court Building.

Dear Ladies, Gentlemen of JCC and friends,

The
Supreme Court of Administration reading will be held on the morning of October 17, 2008

I have been asked. Why it is the Supreme Court of Administration Court decision will be read in Rayong? Because Rayong is the court of record.

The SCofA reading is a formal affair. At the set time the order is received by computer at the court room and printed than give the judge. After the judge receives the order all stand while the Rayong judge read the order aloud into the court record. At this time the decision becomes the law.

We do not try to guess what the order will say. But, our appeal asked the court to either put the injunction back on VT7 or to make the finial decision.

Below is the ending quotation from our appeal:

“the construction control area must be measured from the MSL, onto the land for 200 meters, then it will fulfill the intentions of the regulations of Issue 9 and it will be operative , and truly useful for public. This case has no cause to lift the aforesaid injunction / or revoke the protection procedure to minimize injurious consequences before judgment. With all reasons, facts and matters of laws submitting in this appeal to the Supreme Court of Administration, 9 Litigants need to request for court’s kind consideration to give court’s decision or order to revoke the order of lifting injunction or protection procedure to minimize injurious consequences before judgment of the Administrative Court of Rayong province, as requested by 9 Litigants and with the operative result further on.”

Friday, September 12, 2008

VT7 Explanation to the Supreme Court of Administration

VT7 has responded to our Supreme Administrative Court appeal। Their fist two points of their answer to our appeal have already been rejected by the Supreme Court. The only thing they bring new is the Bangkok Department of City Planning and Civil Engineer office report. This report was not need or we feel it is inaccuracy when it claims to measure into the sea 100 meters from the control construction line at MSL before you measure onto the land 100 meters.

This claim by Bangkok Department of City Planning and Civil Engineer ignore The darting minuted which are part of the regulation। These minutes state measured from the construction control line according to the map annexed, from the sea towards the shore shall not be permitted to construct the following types of buildings (8) Building of 14 meters above the road surface.” “Further amendment was to delete the wording “towards the shore” since the wording was clearly understood,”

We look forward to Supreme Court decision because they have reversely answered The VT7 claims before when in August 2007 they said:

Nevertheless,............. the Ministerial Regulation No. 9...................... prescribed that the 200 meter line measured from the construction control line shown in the map………………….. on the seaside shall be restricted from constructing of any building exceeding 14 meter high from road surface. Therefore, if the Construction Permit No. 162/2007 dated 28 November 2006 granted by the Defendant No. 1 to the Defendant No. 2 should appear to be unlawful against the Ministerial Regulation thereto as being claimed by the ten plaintiffs, the Court of First Instance should have sentenced this point of being unlawful, i.e. the judgment shall be focused on the permission of construction the building exceeding height limit by the Defendant No।

The Supreme Court, therefore, gives an order to amend the order of the Administrative Court of First Instance. That the Defendant No. 2 shall cease the construction performed, under the Work Permit No. 162/2007 dated 28 November 2007, on the part exceeding 14 meter height. On a temporary basis until the Court has ordered otherwise.

Mr. Vorapoj Visarutpich Judge of Supreme Administrative Court”

Translation Copy of document

Supreme Court of Administration vt7 reply


PLAINT No.: 486 / 2008

(Case of the Administrative of Rayong province)

Explanation of 2nd Plaint Receivers Black Case No.: 54 / 2007

( to object the Appeal of the Plaintiffs) Red Case No.: ……………

The Supreme Court of Administration

August 13, 2008

Mr. Tenbult Alewis Maria and 10 Associates Plaintiffs

Between

Pattaya City Hall Official and 2 Associates Plaint Receivers


I, hereby View Thalay Condominium (1999) Co., Ltd., by Mr. Preecha Techamuan- waiwit, the appointed person # 2nd………………........... Plaint Receiver,

Would like to submit this explanation to object “the Appeal against the rejection order of the Administrative of Rayong Province” which ordered to reject the Appeal) of date: February 15, 2008, of the Plaintiff # 1st and Associates ( Plaint No.: 486 / 2008) as will show in the following statements;

1. In this case; by the cause of the Order issued on January 16, 2008

by the Administrative Court of Rayong Province to lift the procedure of minimizing injurious consequences / or temporary protection before judgment, which was the order given to the 2nd Plaint Receiver to temporary seize the construction of the part of the building which was higher than 14 meters above the ground until the judgment or another order is given, therefore, from now ( January 16, 2008) on.

The Plaintiffs lodged the Appeal against the Order of the Administrative Court of Rayong Province which ordered on January 16, 2008 and canceled the temporary procedure of minimizing injurious consequences or protection procedure, which both parties were informed by facsimiles on the aforementioned date.

The Plaintiffs lodged the Appeal against the aforementioned order but the Administrative Court of Rayong rejected that Appeal.

The Plaintiffs then lodged the Appeal against that rejection order to the Supreme Court of Administration, and the Supreme Court was not in agreement with the Administrative Court of Rayong Province, therefore the Supreme Court gave an order to accept the Appeal of the Plaintiffs which lodged on February 15, 2008 to the consideration.

The 2nd Plaint Receiver, by the appointed person: Mr. Preecha Techamuanwaiwit, in capacity of the other party in the appeal, received an order to submit an explanation (Plaint No.: 486 / 2008) from The Supreme Court on July 30, 2008.

The 2nd Plaint Receiver, therefore would like to submit the objection to the Supreme Court of Administration of which will state the matters in the following clarifications.

2. The summary received from analyzing the matters in the Appeal

against the order of January 15, 2008 of the Plaintiffs are ; The Plaintiffs considered that; the Order of lifting Injunction which ordered by the Administrative Court of Rayong province, by using the facts reported by the Department of City Planning and Civil Engineer of Bangkok, issued on December 18, 2007, together with the facts from enquiring the witnesses of this case, the facts revealed that the disputed building is located more than 100 meters from the Mean Sea Level (MSL) which was considered by the court that if the measurement was started from the Construction Control Line as shown in the Annexed map of the Royal Decree, which stipulated the Construction Control Acts of B.E. 2479 to be enforced over the regions of Banglamung Sub-district, Banglamung District, Chonburi province in 2521, which is fixed at a 100 meters from MSL, outward in the sea as shown in the aforementioned Annexed Map and witnesses’ testimony; the dispute building is located over 200 meters from the Borderline of Construction Control Area as stipulated in the Ministerial Regulations of Issue 9 as well. Therefore the facts which had been used by the court to consider placing the injunction / or procedure to minimize injurious consequences before judgment as requested by the 10 Plaintiffs of this case has changed; therefore was unlawful because it was the way of using the facts, construing and enforcing the law by the Administrative Court of Rayong Province in the way which is truly in opposite to the intentions or purposes of the law.

The Plaintiffs therefore requested the Supreme Court to order the injunction to continue being enforced as requested by all Plaintiffs,

3. The 2nd Plaint Receiver would like to inform the Supreme Court that the measurements to find the distance of 100 meters which was measured from MSL to the constructed land had been done for 3 times as follow;

1) The First time had been proceeded by the Pattaya City Hall Official, Chonburi Province; as requested by the 2nd Plaint Receiver in BE. 2548, before this case was submitted in court. The measurement of 100 meters then was started at the MSL of the coastline by the North side. It passed through a public area for 49.00 meters and measured into the dispute land for another 51.00 meters. Then the result would be a 100 meters from MSL. For the south side; It passed through a public area for 49.50 meters and measured into the dispute land for another 50.50 meters. Then the result would be a 100 meters from MSL for this side as shown in the Attachment NO.1.

2) The Second time had been proceeded by the Department of City Planning and Civil Engineering of Chonburi province in April 2007, after the 2nd Plaint Receiver received the order to seize the construction with the dispute license until another order or the judgment is given ( which had caused extreme un-estimated lose and damage to the 2nd Plaint Receiver ) . The second measurement of 100 meters then was started at the MSL of the coastline by the North side. It passed through a public area for 51.00 meters and measured into the dispute land for another 49.00 meters. Then the result would be a 100 meters from MSL. For the south side; It passed through a public area for 49.75 meters and measured into the dispute land for another 50.25 meters. Then the result would be a 100 meters from MSL for this side as shown in the Attachment NO.2.

3) The Third time had been proceeded by The Bangkok Department of City Planning and Civil Engineer officials, which was proceeded between November 15 – 17, 2007, following the order of the Administrative Court of Rayong Province. The result of measurement was shown in the report of December 18, 2007 of that Department which had been submitted to the Administrative Court of Rayong Province. This report showed the correction of the first 2 measurement methods in all details.

4) Considering the Annexed map of the Royal Decree which stipulated to enforce the Construction Control Acts of Be. 2479 over the regions of Nongplalai, Naguea, Nongprue Sub-districts of Banglamung District, Chonburi province in BE. 2521, the result showed that the Construction Control line. Stated in the Ministerial Regulations of Issue 8 (BE. 2519), stipulated following the Construction Control Acts of BE. 2479, and had been amended by the Ministerial Regulation of Issue 9 (BE. 2521), stipulated following the Construction Control Acts of BE. 2521, would be fixed at the 100 meters outward in the sea from the MSL, therefore, when the enquiry of this case by the court showed that the distance of disputed building which received the disputed construction permit of this case is over 100 meters from the MSL. It’s considered without any doubt that the disputed building is also located over 200 meters from the Borderline of Construction Control Area by the seaside. The construction permit is lawful by all stipulations.

The 2nd Plaint Receiver honestly see that the order of lifting injunction /or procedure of minimizing injurious consequences before judgment which had ordered by the Administrative court of Rayong is appropriate.

I, hereby respectfully request the Supreme Court of Administration to give an order or judgment to lift the Appeal of the Plaintiffs.

Respectfully Yours,

- Signed - 2nd Plaintiff

Mr. Preecha Techamuanwaiwit

Appointed person

Wednesday, September 10, 2008

We stop posting on Thaivisa.com forum


Above is one posting which was censored!
I will not be part of Thai visa blog in the future!

I do not agree with censorship। I have continuously had my postings deleted or altered. Thanks to Crow Boy and other of the Thai visa Moderating Team!

Others who support our group have had their posting deleted. There is a group of condo developer who think sharing information of our court action hurts their questionable projects. There is fear of the truth and they feel the truth has hurt their sales on condos.

When one has free speech there is NO big brother taking down ones posting? One side debates are boring!

Our blog is to inform interested people the facts concerning our case and on other blog people attack the fact.

Tuesday, June 24, 2008

The Supreme Court of Administration Decision 19 of June 2008

Order ( Dtoh. 21 )

GARUDA

(Official Emblem )

Number of Petition: 227 / 2551 Number of Order: 313 / 2551

IN THE NAME OF THE KING

The Supreme Court of Administration

23 May 2008

Mr. T, 1st Litigant

Mr. A 2nd

Mr. J , 3rd

Mr. R H 4th

Mr. M 5th

Mr. U 6th

B. 7th

S 8th

B 9th

Mr. M 10th

Between

Plaint Receiver

Officers of Pattaya City Hall 1st

View Thalay Jomtien Condominium (1999) Co., Ltd. 2nd

Matter: The Contentious case involving the misconduct of government officers

( The Appeal against the Rejection Order, refusing to accept the Appeal

against the Order of lifting the Injunction before judgment )

- The Official Stamp of The Supreme Court of Administration -

- Dated: 23 May 2008 -

/ The First Litigant…
1

The 1st Litigant up to 5th Litigant, and 8th Litigant up to 10th Litigant lodged the Appeal against the Order in the Black Case No.: 54 / 2550, of the First Administrative Court ( The Administrative Court of Rayong )

In this case, The 10 Litigants clarified that the 10 Litigants hold

possessions of the condominium units and live in Jomthien Complex Condotel, 1st Building, Located at Thappraya Road, Moo 12, Nongprue Sub-district, Banglamung District, Chonburi Province. The 10 Litigants were damaged by the procedure of 1st Plaint Receiver by issuing the construction license to construct the building with the License No.: 162 / 2550, issued on: 28 November 2549, permitted View Thalay Jomtien Condominium (1999) Co., Ltd. to permanently construct 1 tall building /or an extraordinary large building, type of building: Koh. Soh. Loh., consisting of 27 floors with the roof terrace, 912 units with 24 shops, for living purpose with the total space: 101, 469 Square Meters, parking space: 11, 708 Square Meters – capacities of cars: 418 cars, swimming pool area: 1,134 Square Meters, Length of pipes: 1, 261 Meters, Located in Nongprue Sub-district, Banglamung District, Chonburi Province. The building’s territory is connected to Jomtien Beach by having a garden and Jomtien beach walkway in the middle. As for Jomthien Complex Condotel, it is located on the west side of, and next to the building that received the construction permit which was issued by 1st Plaint Receiver. 1st Plaint Receiver issued the construction permit by being in contrary to the regulations, methods and conditions stipulated in the Ministry Regulations of Issue 9 ( 2521 ), promulgated to be in accordance with the Construction Control Acts of B.E. 2479, clause 3, which fixes the area within 200 meters, by measuring from the Construction Control boundary, that shown on the Annexed Map of the Royal Decree, stimulated to enforce the Construction Control Acts of B.E. 2479 to take control over the regions of Banglamung, Nongplalai, Nakluea, and Nongprue Sub-districts of Banglamung District, Chonburi Province, B.E. 2521, stated that the lands on the sea sides are prohibited from the aforementioned types of buildings to be constructed. And the stipulation of clause 3 ( 8 ) stated that the constructions which is 14 meters high from the road surface are not up to standard requirement to be allowed for construction. The aforementioned Ministerial Regulations was in force on 23 November 2521 until the present time, without amendments or cancellation, however. If the construction would continue until it is complete, it would have been the cause of changing directions of the wind and blocking the wind which normally blows through to Jomthien Complex Condotel, also it would block the beach front view that have been

able to see from the beginning,……………………………………….
2

and Jomtien beach view, which impact physical and mental conditions of the

10 Litigants and also the other residents of Jomthien Complex Condotel. Because the building which was allowed to be constructed by 1st Plaint Receiver is consist of 27 floors / or 81 meters high, which is very close to the height of the condotel that the 10 Litigants live in. After 1st Plaint Receiver issued the license to View Thalay Jomtien Condominium (1999) Co., Ltd. to construct the building, in this present time, the step of landscaping and piling have begun and they caused Jomthien Complex Condotel building to have split and crack lines, also all steps of construction have been done without dust spreading prevention. They caused air pollution and effected respiratory system. The 10 Litigants and residents of Jomthien Complex Condotel had officially tried to object the permission of construction to 1st Plaint Receiver, and also made complaints to involved government sections all along, but the suffering has never been solved, so the 10 Litigants then had to institute the prosecution to the court of law.

The requests for the court to kindly give judgments or orders are as follow;

1. To give an order to minimize the force by suspending the construction license No.: 162 / 2550, Issued on: 28 November 2549 before another order or the final decision is given, and take effect back dated to 28 November 2549. Because 10th Litigants would be extremely damaged until not being able to be solved in the future, if View Thalay Jomtien Condominium (1999) Co., Ltd. still be allowed to continue with its construction.

2. To cancel the construction license No.: 162 / 2550, Issued on: 28 November 2549 which was issued to View Thalay Jomtien Condominium (1999) Co., Ltd. The First Court of Administration gave an order for View Thalay Jomtien Condominium (1999) Co., Ltd. to be an interpleader in this case and determined it to be 2nd Plaint Receiver.

The First Court of Administration made enquiries of both parties on the step of requesting to place the injunction to minimize injured consequences before judgment of the 10 Litigants, and the decision was made as, in this case, the prior point that has been disputed by both parties is the distance from the building, by the Ministerial Regulations of Issue 9 ( B.E. 2521 ), stipulated to be in accordance with the Construction Control Acts of B.E. 2479, which directly involves with the Construction……
3

Control Boundary that shown on the Annexed Map of the Royal Decree, stimulated to use the Construction Control Acts of B.E. 2479 to take control over the regions of Banglamung, Nongplalai, Nakluea, and Nongprue Sub-districts of Banglamung District, Chonburi Province, B.E. 2521. The 10 Litigants and 1st Plaint Receiver have different understanding in the starting point of measurement of the aforementioned Ministerial Regulations. The 10 Litigants fixed the starting point at the lowest point of low tide, but 1st Plaint Receiver fixed the distance of 100 meters outward from highest level of high tide. Therefore, to be able to judge this case, the court needs to inspect carefully and find out the starting point of measurement which was stated in the Ministerial Regulations of Issue 9 ( B.E. 2521), promulgated to be in accordance with the Construction Control Acts of B.E. 2479, also to find out if the distance of the dispute building from that point is not in violation to the law. The inspection will take some time. If the building is still constructed continuously, and if the court would finally revoke the construction license as requested by the 10 Litigants, then it might bring severe damages to the 10 Litigants. This matter gives enough reason for the court to order the Injunction as requested by the 10 Litigants.” The Court, therefore, ordered 2nd Plaint Receiver to seize the construction which had been permitted under the Construction License No: 162 / 2550, Issued on: 28th November 2006 until the final decision or other order is given, since the order have been received.

The 2nd Plaint Receiver, then lodged the Appeal against the order of placing the Injunction to minimize injurious consequences of The First Court of Administration and The Supreme Court of Administration, then gave an supremacy order to amend the order of The First Court of Administration, to be the order of regulating 2nd Plaint Receiver to temporally seize the steps of construction under the construction license No.: 162 / 2550, Issued on: 28th November 2006, only for the part of the building which is higher than 14 meters from the road surface until the decision is given or another order is made by the court.

The First Court of Administration has preceded the enquiry by ordering the Department of Civil Engineering and City Planning to measure and find the distance between the coast line at the Mean Sea Level (MSL) which is in accordance with the Royal Decree, stimulated to use the Construction Control Acts of B.E. 2479 to take control over the regions of Banglamung,………………..
4

Nongplalai, Nakluea, and Nongprue Sub-districts of Banglamung District, Chonburi Province, B.E. 2521, to the dispute building, together with the order to present to the court the brief layout or chart, which the layout was made as ordered and presented by the Department of Civil Engineering and City Planning, summarizing that, to fix the coast line at Mean Sea Level, the measurement must be started at the point of 0.00 meters of the Mean Sea Level. When the measurement is made 100 meters outward to the sea, then it will be the Construction Control Boundary that shown on the Annexed Map of the Royal Decree, stimulated to use the Construction Control Acts of B.E. 2479 to take control over the regions of Banglamung, Nongplalai, Nakluea, and Nongprue Sub-districts of Banglamung District, Chonburi Province, B.E. 2521, then made another 100 meters from the aforesaid point into the land, then it will be the distance of 200 meters of the Construction Control Boundary, as stipulated in clause 3 of the Ministerial Regulations of Issue 8 ( B.E. 2519 ), stipulated to be in accordance with the Construction Control Acts of B.E. 2479, which had been amended by adding the Ministerial Regulations of Issue 9 ( B.E. 2521), which stipulated to be in accordance with The Construction Control Acts of B.E. 2479, which stated to prohibit the building with the height over 14 meters from the road surface. The measurement result reported that the building of 2nd Plaint Receiver is not in the boundary of 200 meters.

2nd Plaint Receiver requested the First Court of Administration to lift the injunction before the decision is made.

The First Court of Administration questioned both parties and witnesses and considered that, in this case, the court ordered to temporally place the injunction before the decision is made as requested by the 10 Litigants with the prior reason that, to proceed enquiries of this case, the court needs to inspect carefully and find out the starting point of measurement which was stated in the Ministerial Regulations of Issue 9 ( B.E. 2521), promulgated to be in accordance with the Construction Control Acts of B.E. 2479, also to find out if the distance of the dispute building from that point is not in violation to the law. But the measurement following the order of court, reported by of the Department of Civil Engineering and City Planning, together with the witness’s testimony, stated that, the dispute building is located more than 100 meters from the Mean Sea Level. With the consideration of court, considering the measurement of 100 meters, from the Mean Sea Level, outward into the sea which was reported and testified by the witness, to be the Construction Control Boundary, shown on the Annexed map of the Royal Decree, which stipulated to enforce the Construction Control Acts of ………
5

B..E. 2479, to take control over the regions of Banglamung, Nongplalai, Nakluea, and Nongprue Sub-districts of Banglamung District, Chonburi Province, B.E. 2521, the contrary building will be over 200 meters of the Construction Control Boundary, and also as stipulated in the aforementioned Ministerial Regulations. Therefore, the matters of facts which have been used in consideration of court have changed, and the reasons to continue placing the Injunction becomes insufficiency. The court then, ordered to lift the Injunction which was the order of stopping the 2nd Plaint Receiver from building the construction higher than 14 meters from the road surface temporally, until the final decision or the other order is given, following Clause 77 of the regulations of the Grand Administration Meeting of the Supreme Court of Administration, governing the Administrative Procedures of B.E. 2543, together with Article 262, Phrase 1 of the Civil Codes, which have brought in to be enforced compromisingly.

7th Litigant withdrew his name out of being one of all litigants, by the document dated on 17 January 2551 and the First Court of Administration permitted the withdrawal of 7th Litigant.

1st – 6th and 8th – 10th Litigants lodged the Appeal dated on 15 February 2551 against the order of lifting the injunction given by the First Court of Administration. The request was asking for the supremacy order from the Supreme Court of Administration to amend the order given by the First Court of Administration, and to order the injunction to be able to continue taking effect before judgment as requested by the 9 Litigants.

The First Court of Administration considered that, as stated in Clause 76, 2nd and 3rd phrases of The Regulations of the Grand Administration Meeting of the Supreme Court, governing the Administrative Procedures of B.E. 2543, it shows that, there are only 2 circumstances involving the consideration about the injunction before judgment during trials by the Administrative Court. One is the circumstance of which the court gives the order to reject or lift or cancel the request of the litigant, this type of order is considered to be the supremacy order, and the other circumstance is in the case of which the court gives the order to place the injunction, the interested person has the right to lodge the Appeal against this order, temporally, the interested person has the right to lodge the Appeal to the Supreme Court of Administration. In this case, the court originally gave an order to place the injunction to minimize injurious consequences…..
6

Before judgment as requested by the 9 Litigants. The 2nd Plaint Receiver, therefore, used the right to lodge the Appeal to the Supreme Court of Administration, and the Supreme Court already gave the order to replace the former order which was given by the First Court of Administration. When later on, the facts and reasons to continue placing the injunction became insufficiency. The court then, cancelled the aforementioned order to minimize injurious consequences. This circumstance, however, gave the same effect as the rejection / or cancellation of the request which was requested by the 9 Litigants, therefore, this order is the supremacy order as stated in Clause 76, 2nd Phrase of the aforesaid Regulations, and the 9 Litigants can no longer lodge the Appeal. This Appeal of the 9 Litigants is forbidden to be proceeded by law, the First Court of Administration then gave the order to reject the Appeal of the 9 Litigants.
6th Litigant withdrew his name out of being one of all litigants, by the

document dated on 20 February 2551 and the First Court of Administration permitted the withdrawal of 6th Litigant.
1st – 5th and 8th – 10th Litigants lodged an appeal against the rejection order which refused to accept the appeal against the order of lifting the injunction before final decision is made, given that order by the First Court of Administration, the matters stated that, the order given out to lift the Injunction is another step of trial and ordering after the injunction was ordered by the First Court of Administration and the Supreme Court of Administration, to be placed before the final decision is made / and it is NOT the order that would give the same effect to reject / or cancel the request which was filed by the 8 Litigants, because that order is the final order and it is prohibited for appealing, as stated in Clause 76, 2nd Phrase of the mentioned Regulations. Because of no stipulation in the aforesaid law / or regulations to state that, the order of lifting the injunction before judgment, given by the First Court of Administration is the FINAL ORDER The aforesaid order……….
7

is considered to be another type of order, which is allowed to appeal during trial, as stated in Clause 100, 2nd phrase, which stated that the interested persons have the right to lodge an appeal against the aforesaid order, to the Supreme Court of Administration within 30 days from the day of receiving that order, given by the First Court of Administration, as stated in Clause 49 /1 and Clause 100, 1st Phrase of the Regulations of the Grand Administrative Meeting of the Supreme Court, governing the Administrative Procedures of B.E. 2543, which is in agreement with the point of law in the Civil Codes, which stipulated the right to lodge an appeal against the amending order / or canceling order, which is temporally, and stated in Article 262, is the order that is allowed to appeal, and according to Article 228 (2 ) of the Civil Codes, the appeal must be lodged within 30 days. Also the points in the appeal of the 8 Litigants are suitable to be taken for consideration for the judgment to be given by using the standard in consideration of the Supreme Court of Administration. Therefore, the request which was made to the Supreme Court of Administration is for the Supreme Court of Administration to give the supremacy order to change the order of the First Court of Administration, by ordering to accept the appeal of the 8 Litigants for consideration.
The Supreme Court of Administration considered and acknowledged that, the stipulation in Clause 75 of the Regulations of the Grand Administrative Meeting of the Supreme Court stated that, apart from the circumstance which mentioned in Clause 69, at all times, before the final court decision is given, the litigant may institute the petition to request for any procedure to minimize the injurious consequences before the final court decision is given, / or the other party may file the request for the court to order the procedure to protect the benefit during trial / or to enforce the act follow the court’s decision. In Clause 76, 2nd Phrase, stipulated that the cancellation or rejection order against the petition of request of the litigant is the supremacy order. And in 3rd Phrase stipulated that, the interested persons have the right to lodge an appeal against the order of placing the procedure to minimize the injurious consequences before the judgment is given / or the procedure to protect the benefit of the litigant during trial, / or to enforce by the court’s decision, to the Supreme Court of Administration within 30 days from the day of receiving or being informed about that order. In Clause 100, 1st Phrase, stated that, the court’s decision / or order given by the First Court of Administration, which has not been stipulated to be the supremacy or final order, can be appealed to the Supreme Court of Administration, and in 2nd Phrase, stated that, the order during trial which has not been stipulated by this regulations to be able to appeal during trial, must be appealed together with the appeal against the judicial decision / or order that finalize the case out of the consideration of court. And in Clause 49 / 1, 1st Phrase, stated that, the order of the First Court of Administration which refusing to accept the petition for consideration, ………….
8

the order of disposing the case out of record without the definite final decision, / the order of punishment the charge of infringement of the jurisdiction of courts following the Article 64 / or another orders which are not prohibited to appeal during trial by Clause 100, 2nd Phrase, stated that, the interested persons have the right to lodge an appeal against the aforementioned orders to the Supreme Court of Administration within 30 days since receiving the order given by the First Court of Administration. And in 2nd Phrase, stated that, the petition stated in 1st Phrase shall be lodged to the First Court of Administration which given out that order, and the court officer shall send the petition, together with the order of the First Court of Administration, also involved documents / or copies of documents, immediately, to the Supreme Court of Administration.

In this case, originally, The First Court of Administration ordered to

place the Injunction to minimize injurious consequences by ordering 2nd Plaint Receiver to seize the construction under the construction license NO.: 162 / 2550, Issued on: 28th November 2006, until receiving another order or the judgment. 2nd Plaint Receiver, then lodged an appeal against the order of placing the injunction, given by the First Court of Administration, / and the Supreme Court of Administration had given the supremacy order to change the former order of the First Court of Administration by ordering 2nd Plaint Receiver to seize the construction under the construction license NO.: 162 / 2550, Issued on: 28th November 2006, only for the part of the building which is higher than 14 meters from the road surface until the decision is given or another order is made by the court. When the First Court of Administration has preceded the step of enquiry by ordering the Department of Civil Engineering and City Planning to measure and find the distance between the coast line at the Mean Sea Level (MSL) , together with presenting the brief layout or chart to the court, the Department of Civil Engineering and City Plannin reported to the court that,

the contrary building is located outside the Construction Control Boundary, as shown on the Annexed Map of the Royal Decree, stimulated to enforce the Construction Control Acts of B.E. 2479 to take control over the regions of Banglamung, Nongplalai, Nakluea, and Nongprue Sub-districts of Banglamung District, Chonburi Province, B.E. 2521, along the seaside, more than 200 meters, as stipulated in Clause 3 of the Ministerial Regulations of Issue 8 ( .E. 2519 ), which stipulated to be in accordance with the Construction Control Acts of B.E. 2479, which had been amended by adding the Ministerial Regulations of Issue 9 ( B.E. 2521), which stipulated to be in accordance with The Construction Control Acts of B.E. 2479. 2nd Plaint Receiver then, lodged a petition to request for the cancellation of the injunction before final court’s decision is made, and the First Court of Administration then making enquiries, by questioning both parties ………………
9
and the witnesses, and then considered that, the matters of facts which have been used in consideration of court have changed, and the reasons to continue placing the Injunction becomes insufficiency for the order to remain the same. The court then, ordered to lift the Injunction which had been the order of stopping the 2nd Plaint Receiver from building the construction higher than 14 meters from the road surface temporally, until the final decision or the other order is given, following Clause 77 of the regulations of the Grand Administration Meeting of the Supreme Court of Administration, governing the Administrative Procedures of B.E. 2543, together with Article 262, Phrase 1 of the Civil Codes, which have brought in to be enforced compromisingly.

Even though the order of lifting the injunction before final decision is made, which given by the First Court of Administration, shall take the same effect to the rejection or cancellation of the request which was filed by the litigants, which was the request to place the injunction, however, it is NOT THE ORDER OF LIFTING OR CANCELLING THE REQUEST of the litigants which requested the court to temporally place the injunction before the final court’s decision is made.

The Supreme Court of Administration is however, not in agreement with the consideration of the First Court of Administration on the matter that the First Court of Administration considered the effect of the order of lifting the injunction to be as same effect taken by the rejection or cancellation of the request which was filed by the litigants, which was the request to place the injunction before the final court’s decision is made. The aforementioned order is stipulated to be the supremacy order as stated in Clause 76, 2nd Phrase of the regulations of the Grand Administration Meeting of the Supreme Court of Administration, governing the Administrative Procedures of B.E. 2543. And thereby, the order of lifting the injunction given by the First Court of Administration is the type of order which was not stipulated to be the supremacy order, following the Administrative Control Acts and the Administrative Procedures of B.E. 2542 / and the Regulations of the Grand Administrative Meeting of the Supreme Court, governing the Administrative Procedures of B.E. 2543, the litigants have the right to appeal to the Supreme Court of Administration by following Clause 100, 1st Phrase of the mentioned regulations.
The only issue that needed to be taken to the consideration will be about the order of lifting the injunction / or canceling the protection procedure to minimize the injurious consequences before final court’s decision is made, ………
10

Given by the First Court of Administration is either the order during trial which is prohibited to appeal during trial, as stated in Clause 100, 2nd phrase of the same regulations / or NOT.

The result of consideration agreed that, while the contentious case between the 8 Litigants and 2 Plaint Receivers is on trial of the First Court of Administration, the order of lifting the injunction or procedure to minimize injurious consequences which was the order for 2nd Plaint Receiver to seize the construction under the construction license No.: 162 / 2550, Issued on: 28 November 2549, only for the part of the building that is above 14 meters from the road surface, until receiving the Judicial decision or another order, which given by the First Court of Administration, is NOT the judicial decision or order to finalize the case out of court’s consideration, so it is considered that, the aforementioned order is an order during trial. Even though there is no obvious stipulation which is clearly clarified the right to appeal in the regulations of the Grand Administrative Meeting of the Supreme Court, governing the Administrative Procedures of B.E. 2543, unlike the obvious stipulation of which stipulated the right of the interested persons, in able to lodge an appeal against the order of lifting the injunction during trial of the First Court of Administration, however, but it is shown by the reason of the matter that, The Litigants should receive the same right as the interested persons receive to be able to lodge an appeal against the order of lifting the injunction before judgment, during the trial. Allowing the litigants to lodge an appeal against the aforementioned order, including against the judicial decision / or the court order which definitely finalize the case out of court’s consideration and trial, as stated in Clause 100, 2nd phrase of the regulations of the Grand Administrative Meeting of the Supreme Court, governing the Administrative Procedures of B. E. 2543, will not benefit the litigants. Thereby, if the Supreme Court of Administration considers that the matters in the appeal of the litigants is strong, the litigants will loose the temporally protection during trial of the First Court of Administration IN TIME, the matter is considered that the order of lifting the injunction during trial, given by the First Court of Administration is NOT THE PROHIBITED ORDER for appealing during trial, as stated in Clause 100, 2nd phrase of the regulations of the Grand Administrative Meeting of the Supreme Court, governing the Administrative Procedures of B. E. 2543. Therefore, the 8 Litigants, then have the right to lodge an appeal against the aforementioned order to the Supreme Court of Administration within 30 days from the day of receiving the order given by the First Court of Administration, as stated in Clause 49 /1, 1st phrase of the mentioned regulations. The First Court of Administration should…………
11

should assign the court officer to send the Appeal against the order dated on 15 February 2551 of the 8 Litigants, including the order of lifting the injunction given by the First Court of Administration and all involving documents / or copies of documents to the Supreme Court of Administration within the short period of time, following Clause 49 / 1 of the same regulations। The decision of giving out the rejection order against the appeal of the 8 Litigants, is not in the agreement with the consideration of the Supreme Court of Administration.

The court, hereby shall give the order to accept the Appeal against the order, dated: 15 February2551 of the 8 Litigants to take under court’s consideration.

Mr. Worapoj Wisarupitch - Signed - (Responsible Judge)

Judge of the Supreme Court of Administration

Mr. Ampol Sighagowin - Signed -

Chief of Judges of the Supreme Court of Administration

Mr. Wichai Cheunchompunoot - Signed -

Judge of the Supreme Court of Administration

Mr. Paiboon Sianggong - Signed -

Judge of the Supreme Court of Administration

Mr. Udomsak Nitimontri

Judge of the Supreme Court of Administration

/ attachment – the record of the Supreme Court of Administration

In the case of the necessity of the absent of the signature of the judge.

- The Official Stamp of the Supreme Court of Administration -

- The Official Stamp of The Supreme Court of Administration -

- Dated: 23 May 2008 - 12

************************************************************************

Compare the Supreme Administrative Court decide given in Rayon on 1 of August 2007 with the most recent.

“The point to be considered further is that whether it is reasonable and justified to apply provisional measure or temporary safeguard before judgment as requested by the ten plaintiffs. The judge considered that while the plaintiffs are filing the case, the building is being constructed by the Defendant No. 2. The construction is preparing the land site, foundation piles are being knocked down into the base soil. The knocking was so hard that the condominium of the ten plaintiffs was cracked. Construction was processed without dust cover or protection resulting air pollution. While the Administrative Court of First Instance examining the parties to apply the temporary protection or provisional measure before judgment, the lawyer authorized by the ten plaintiffs testified that the construction has already passed the foundation piles knocking. Pillars are being formed up. This verifies that the Defendant No.2 intends to continue the construction. The plaintiffs, who live in Jomthien Complex Condotel Condominium, as well as other neighboring residents in the construction areas, can possibly be suffered and damaged from the construction as being stated in the motive, i.e. while the building going taller or higher, the wind direction from Jomthien sea can change its direction and not blowing towards Jomthien Complex Condotel like before. The sea scenery shall be blocked off by the new building disrupting the good health of the existing residents. As the building being constructed by the Defendant No. 2 is as high as 27 storeys, or about 81 meters which is close the height of the condominium being stayed by the plaintiffs. Therefore, if the construction of disputed building continues, it is difficult to remedy the problem at a later date because if the Court revokes the construction permit at the end of the trial, the building shall be demolished accordingly to the Court’s order. The demolishing should require long period to accomplish. As long the building was not completely demolished, the ten plaintiffs shall be suffered by the building. Besides, the demolishing cannot serve as the remedial action to the disturbance or damage the plaintiffs have already suffered before the demolishing completed.

The circumstance is justified to the Court to order provisional measure, or give temporary protection before judgment that the Defendant No. 2 temporary ceasing the construction of the building according to the Construction Permit No. 162/2007 dated 28 November 2006 until the Court gives judgment or orders otherwise.

The last question to be considered is that whether the provisional measure before judgment shall render negative effect to the Defendant No. 1 on their routine administration. The consideration was that when the Court has the order to give temporary protection and issuance of the provisional measure to cease the construction of the building is only involved with the construction work at the site. There is nothing to enforce or change or to affect whatsoever to the Work Permit that the Defendant No. 1 issued. Therefore, the Court’s order is not interfering with the administration of the Defendant No. 1

Nevertheless, where No. 3 (8) under the Ministerial Regulation No. 8 (B.E. 2519) issued by the virtue of the Building Control Act B.E. 2479 amended by the Ministerial Regulation No. 9 (B.E. 2521) issued by the virtue of the Building Control Act B.E. 2479 prescribed that the 200 meter line measured from the construction control line shown in the map annexed to the Royal Decree promulgating the Building Control Act B.E. 2479 governing Tambol Bang Lamung, Tambol Nhong Plalai, Tambol Na Klue and Tambol Nhong Prue of Ampur Bang Lamung Chonburi Province B.E. 2521 on the seaside shall be restricted from constructing of any building exceeding 14 meter high from road surface. Therefore, if the Construction Permit No. 162/2007 dated 28 November 2006 granted by the Defendant No. 1 to the Defendant No. 2 should appear to be unlawful against the Ministerial Regulation thereto as being claimed by the ten plaintiffs, the Court of First Instance should have sentenced this point of being unlawful, i.e. the judgment shall be focused on the permission of construction the building exceeding height limit by the Defendant No. 2. Whilst the Administrative Court of First Instance ordered the provisional measure to cease construction before judgment, the building’s base rocks were built, the construction did not reach the height limit of 14 meter above the road surface. Where the Administrative Court of First Instance issued the order of provisional measure to effect temporary protection by ceasing the entire construction is, therefore, in excess of what reasonable under the circumstances.

The Supreme Court, therefore, gives an order to amend the order of the Administrative Court of First Instance. That the Defendant No. 2 shall cease the construction performed, under the Work Permit No. 162/2007 dated 28 November 2007, on the part exceeding 14 meter height. On a temporary basis until the Court has ordered otherwise.

Mr. Vorapoj Visarutpich

Judge of Supreme Administrative Court

Mr. Amnaj Singgovin

Chief Judge of the Supreme Administrative Court

Mr. Vichai Chuenchompoonuj

Judge of Supreme Administrative Court

Mr. Paiboon Siengkong

Judge of Supreme Administrative Court

Mr. Udomsak Nimitmontri

Judge of Supreme Administrative Court

*********************************************************************************

Below is the English translation of the Department of Public Works and Town & City Planning in Bangkok report to Rayong Administrative Court. It starts with a letter mark “most urgent” dated 18 December 2007.

“MOST URGENT
GARUDA EMBLEM

Ref. Mor Tor 0710/9634
Dept. of Public Works
And Town & City Planning
Rama 6 Road, Phayathai
Bangkok 10400
18 December 2007

Subject Execution of Court Order
To The Director General of Rayong Administrative Court
Reference Order of Rayong Administrative Court dated 19 September 2007

Enclosure 1. Execution Report to Court Order with support document
.Photos taken to support the report

With reference to the Order of Rayong Administrative Court issued to the Department of Public Works and Town & City Planning, as the authority who responsible for the issuance of the Royal Decree Promulgating the Building Construction Control Act B.E. 2479 applying to some areas of Tambol Bang Lamung, Tambol Nhong Plalai, Tambol Na Klua and Tambol Nhong Prue of Amphur Bang Lamung of Chonburi Province B.E. 2521 and the Ministerial Regulation No. 8 (B.E. 2519) amended by the Ministerial Regulation No. 9 (B.E. 2521) issued under the Building Construction Control Act B.E. 2479 executing the measurement of distance of Mean Sea Level under the provision of the above Decree to the building under conflict. The measured distance shall be reported to the Court supporting by the map, The Department of Public Works would advise that our officers have been assigned to execute the Court Order since 15 through 17 of November 2007. The measurement report with related photographs recorded during the execution are attached (Attachment 1 and 2 referred).

Yours respectfully

(Mr. Suraphol Phongthaipat)
Senior Engineer
In charge of the Director of the Dept. of Public Works

Building Control and Inspection Division "

The Report concerning the court order survey is below:

"Execution to Court Order Report

1. Original Story

The Rayong Administrative Court has its Order Black Case No. 54/2550 between Mr. Tenbuelt Aloysius Joannes Maria, No. 1 and 9 Associates totaling 10 Litigants and the Pattaya City Local Official, No. 1 Prosecuted Person and the No. 2 Prosecuted Person, Order dated 19 September 2007 referred.

The Department of Public Works being the authorized agency as the authority who responsible for the issuance of the Royal Decree Promulgating the Building Construction Control Act B.E. 2479 applying to some areas of Tambol Bang Lamung, Tambol Nhong Plalai, Tambol Na Klua and Tambol Nhong Prue of Amphur Bang Lamung of Chonburi Province B.E. 2521 and the Ministerial Regulation No. 8 (B.E. 2519) amended by the Ministerial Regulation No. 9 (B.E. 2521) issued under the Building Construction Control Act B.E. 2479 executing the measurement of distance of Mean Sea Level under the provision of the above Decree to the building under conflict. The measured distance shall be reported to the Court supporting by the map, after measurement is complete, the Department shall submit report with supporting map to the Court.

The Department of Public Works has assigned the following 8 staff members from the Building Inspection and Control Division accompanied by the Engineers of the Structural and System Engineering Division to accomplish the measurement

2. Staff involved

1. Mr. Viriya Visutrattanakul Legal Officer 7 Building Control and Inspection
2. Mr. Wattanachat Kajornsiri Civil Engineer 6 System Engineering Div.
3. Mr. Suthichai Boonlam Civil Engineer 4 System Engineering Div.
4. Mr. Vichet Chaithong-at Civil Engineer 2 System Engineering Div.
5. Mr. Soonthorn Vejpitak Civil Officer System Engineering Div.
6. Mr. Puchong Chansomboon Worker System Engineering Div.
7. Mr. Thongchai Yangsoong Worker System Engineering Div.
8. Mr. Thanivat Jangploy Driver Building Control and Inspection

Observers from the Litigants

1. Mr. Richard ............. Litigant
2. Mr. Adam ........ Litigant
3. Mr. Amnaj Thiengtham Authorized Lawyer
4. Mr. Rigis ........ Observer
5 मर्स Observer
6 Mrs Benyaporn Observer
7. Mr. Tanes Tumthong Lawyer‘s Representative
8. Mr. Chalermchat Vanitsirisit Lawyer’s Representative
9. Asst. Prof. Dr. Sanpetch Surnitipaisan Engineering Division, Chulalongkorn University

Observers from the Prosecuted Person 1 Pattaya City

1. Mr. Vidhaya Sirivorachai Chief Building Control Division
2. Mr. Samran Panpreecha Chief Building Control Section
3. Mr. Chavalit Jariyayanyong Traffic Researcher 7
4. Miss Benjawan Chinpat Legal Officer 4
5. Mr. Teeradej Srimuang Inspector Region 3

Observers from the Prosecuted Person 2 View Talay Jomthien (1999) Company

1. Mr. Somjet Hasan Project Engineer
2. Mr. Preecha Dechamuanvaivit Authorized Lawyer
3. Mr. Jeerasak Sangvanlek Observer
4. Mrs. Vilai Supcharoen Observer

Observer from the Meteorological Department
Mr. Jaruwat Srichana Meteorological Officer 6

3. Period of execution
The process had been operated from Thursday 15 November 2007 to Saturday 17 November 2007 for 3 days.

4. Methods
The measurement started from the brass peg No. Or Dor MSL C.B. 0029 which is 48.989 meter above mean sea level at the area of Chonburi Meteorological Department (Pattaya) on Phra Tamnak Hill targeted by survey telescope through the road towards the entrance of Royal Cliff Hotel to reach the Phra Tamnak 5 Road then leftward into Phra Tamnak 5 Road until the telescopic sight reach Jomthien Beach on the footpath level then further down to the construction area in dispute (before Dong Tan Police box). The distance was about 3.5 kilometer. Next step was by telescopic survey from the site of dispute backward to the brass peg MSL C.B. 0029 at the distance of again 3.5 kilometer to recheck the precision of measurement. In each measured point, temporary B.M. or B.M.T had been marked all the way as requested by the observer of the litigants. Two sets of temporary M.T. were marked again in front of the Jomthien Beach exactly in front of the construction site after precise leveling equivalent process was carried out. One set was marked at the MSL of 0.00 meter and the other was marked at MSL of 1.4477 meter. Measurement of distance from the two marked point to the conflict building was recorded in the presence of both parties. The parties were satisfied with the process therefore accepted the execution method carried out by the Department of Public Works (Attachment 1 refers).


5. Execution results
The reading from telescopic survey process to identify MSL appeared in the horizontal line herewith attached (Attachment 2 refers) and from the examination on MSL, referred to in the Book printed in the memorial of the Meteorological Department on its 80th Anniversary Chapter 5 page 88, published on 10th January 2007 claimed that the MSL value equals to 0.00 meter. The MSL of 1.4477 meter is the reference MSL at Ko Lak area of Prachuab Khirikhan Province. This is the reference MSL used by the Ordnance Survey Department throughout the country by means of leveling transfer (Attachment 3 refers). Therefore, the measurement of MSL at the shoreline must be measured from MSL 0.00 seaward to the distance of 100 meter is the area for construction restriction appeared in the map annexed to the Royal Decree Promulgating the Building Construction Control Act B.E. 2479 applying to some areas of Tambol Bang Lamung, Tambol Nhong Plalai, Tambol Na Klua, and Tambol Nhong Prue of Amphur Bang Lamung of Chonburi Province B.E. 2521.

Where the measure from this point toward the land in front of the building construction for another 100 meter, the area shall be identified as the 200 meter restriction area for construction referred under Clause 3 of the Ministerial Regulation No. 8 (B.E. 2519) amended by the Ministerial Regulation No. 9 (2521) issued under the Building Construction Control Act B.E. 2479 governing restriction of construction of the building exceeding 14 meter from ground level. Measurement result is appeared in the attached map (Attachment 4 refers).

Report prepared by
Mr. Wattanachart Kajornsiri

Certified Correct Copy
Mrs. Suthida Chiengpongse
Administrative Case Officer “

हाउ can anyone read Issue 9 and make this report? Look at what Issue 9 said “No 3. To specify the area within the 200 meters measurement from the construction control line see the map.......................at the seashore in which the following constructions shall not be built:” “Building of 14 meters higher than road level”

There is no where in Issue 9 it said to measure seaward 100 meters from MSL! Then to measure 100 meters from MSL onto the land। After which you add the two measurements together for a 200 meters measurement from the seashore at MSL.

***************************************************

Witness Testimony Record

(Inquiring Stage)

Black Case No. 54/2551

GARUDA EMBLEM

The Administrative Court of Rayong

15 January 2008

Mr. Tenbuelt …………….. No. 1 and 9 Associates Litigants

Between

Pattaya City Local Official First Prosecuted Person

View Talay Jomthien Condominium Second Prosecuted Person

I have taken an oath to testify the following statement:

  1. My name is Mr. Veera Visuthirattanakul
  2. I was born on 28 June B.E. 2500 age 50
  3. My profession is Legal Officer 7
  4. I reside at The Office of Building Control and Inspection within the Department of Public Works and Town & City Planning, Rama 6 Road, Khwang Samsennai, Khet Phayathai, Bangkok
  5. My relationship to the parties : Witness

My testimony shall be as follows:

The restricted zone of the building control area under the Royal Decree governing Building Construction Control B.E. 2521 shall be determined by the distance of 100 meter from Mean Sea Level outward to the sea.

In conducting the measuring, the witness did not measure from MSL towards the conflict building, but measured from the MSL to the 100 meter from the MSL

Mr. Veera Visuthirattanakul, Legal Officer 7 and Mr. Wattanchart Kajornsiri, the Civil Engineer 6 of the Department of Public Works are the witnesses of the case.

The Litigants apply the motion to clarify the point of law and fact dated 15 January 2008. The motion was accepted by the Court and copy of this motion was given to the two prosecuted persons today.

The testimony of the parties and witnesses have been recorded by the Court.

All parties and witnesses requested copies of the witness testimony records together with proceeding report of today. The Court approved such requests.

All witnesses received witness’ fee of Bht 300 each and transportation cost of Bht 1,000 each. Each witness received total 1,300 baht.

The hearing closed at 10.45 hours.

Signed ……………………………………………. Judge of the file

(Mr. Kritdanai Tromtat)

************************************************************

Motion

The Rayong Administrative Court

2 January 2008

Mr. Tenbuelt Aloysius Joannes Maria No. 1 and 9 Associates Litigants

Between

Pattaya City Local Official First Prosecuted Person

View Talay Jomthien Condominium Second Prosecuted Person

I, View Talay Jomthien Condominium (1999) Company Limited by Mr. Preecha Techamualvaivit, the authorized lawyer …………………………………………. of the Prosecuted Person 2 would file the motion as follows:

The inquiring process to all parties and witnesses – Mr. Veera Visuthirattanakul and Mr. Wattachart Kajornsiri have been completed since 15 Januray 2007. The Court also sent the copy of the MOST URGENT letter reference Mor Tor 0710/9634 issued by the Department of Public Works and City & Town Planning to the parties.

  1. Report of execution to Court Order that accomplished by the officials of the Department of Public Works and Town & City Planning from the central office, after which the results are as follows:

(1) Measurement from shoreline at 0.00 MSL at the north side of the land of conflict towards the land mark foundation is 50.15 meter and if further measure into the land plot of another 49.85 meter the total distance will be 100 meter measured from the shoreline at MSL 0.00 at this side.

(2) Measurement from the shoreline at 0.00 MSL at the south side of the land of conflict towards the land mark foundation is 49.60 meter and if further measured into the land plot of another 50.40 meter the total distance will be 100 meter measured from the shoreline at MSL 0.00 at this side.

(3) The high-rise building line that will be constructed on the land of conflict towards the seaside by meter meters behind 100 meter line.

(Please see details in the enclosed map of measuring according to the Court Order)


As the measurement of 100 meter referred in No. 2 above, it is verified that the building in conflict is not built in the restricted area of 200 meter as prohibited by the Construction Permit No. 162/2550