Wednesday, August 8, 2007

August 8 Admin Court hearing in Rayon has not concluded our case

Pattaya City hall and VT7 could not agree with Department of Civil Engineering and City Planning from Bangkok explanation of issue 9. They keep confusing how to measure from MSL.

The Bangkok man could not answer any of the judge’s questions which were not written in his office letter. This left unanswered questions.

The court is going to order the Thai Port Authority and the Bangkok Department of Civil Engineering and City Planning to take measurement and make a map for the court. The map will show where VT7 building is located as to issue 9 alignment.

The stopvt7 group is going to hire an expert to watch over the taking of measurement and making of the map.

VT7 can keep working but not build over 14 meters high.

Their will be another court hearing.

The Bangkok letter form Department of Civil Engineering and City Planning explains the following?

    1. The distance of 100 meters in Issue 8 and the distance of 200 meters Issue 9 are not the same alignment.
    2. Issue 9 specified that the measurement of the alignment of the cost line be taken only at MSL (mean sea level). This setting 200 meters measured from MSL for alignment of alignment before you can build over 14 meters.
    3. City Hall and VT7 as made false claims in court by claim Issue 8 and Issue 9 as the same alignment before you can build over 14.

Quote from Mr. Surapol 19 of June 2007 Department of Civil Engineering and City Planning Bangkok letter: “The distance of 100 m as per point 3 of the Ministerial Regulation Issue 8 (B.E. 2519) issued pursuant to the Building Control Act B. E. 2479 and the distance of 200 m. as per point 3 of the Ministerial Regulation Issue 9 (B.E. 2521) issued pursuant to the Building Control Act B. E. 2479 are not the same alignment. In that the alignment of the coat line in accordance with the Ministerial Regulation Issue 8 (b. E. 2519) had not specified the measurement be taken at MSL. But in accordance with the Ministerial Regulations Issue 9 (B. E. 2521) it specified the measurement of the alignment of the coast line be taken only at MSL.”

Chief Engineer Acting on Behalf of the Director General
Department of Civil Engineering and City प्लानिंग


Where was in writing the claim to measure into the sea started? It was from Pattaya City Hall Explanations to the court. Fine a English translation below!


Asia LawWorks Co., Ltd.

A t t o r n e y s – a t – L a w
R e c h t s a n w ä l t e


TRANSLATION OF BLACK CASE NO. 54/2550
EXPLANATION OF CITY HALL DATED 4TH APRIL 2007


Garuda
Royal Insignia
Explanations Case Black Number 54/2550

Administrative Court, Rayong

4th April 2007

Mr. T….. A, Jo, Maria 1 and Group, 10 in all plaint makers

Between

Competent officer of locale of Pattaya City 1
And group altogether 2 plaint receivers

I, the competent officer of locale of Pattaya City, Mr. Niran Wattanasartsathorn, plaint receiver, address Pattaya City Hall, North Pattaya, Nongprue, Banglamung, Chonburi 20260 Tel. 038-253242-3 have understood the plaint throughout and would like to give explanations and facts as follows:

1. Mean sea level means the average of sea water at high tide and low tide calculated by the Department of Hydrography of the Navy with a point of reference at Koh Lak, Prachuab Kiri Khan province and used this level as the reference point in Thailand, for instance at the Land Office there shall have a mean sea level as point of reference to be referred to (as per document 1).
2. According to the Ministerial Regulations Issue 8 (B.E. 2519) issued pursuant to the Buildings Control Act B.E. 2479, point 3 stipulating an area within 100 m. measuring from the building construction control line as per map attached to the Act, effective as the Buildings Control Act B.E. 2479 in the locale of Banglamung sub-district, Naklua sub-district and Nongprue sub-district, Banglamung district, Chonburi province B.E.2479 on the seafront side a building having the height above 14 m. from road level may not be erected. The alignment of the buildings construction control pursuant to the Ministerial Regulations Issue 8 was the same alignment with the alignment of the coastline at the median sea level as per map attached to the Act above.
3. According to the Ministerial Regulations Issue 9 (B.E. 2521) issued pursuant to the Buildings Control Act B.E. 2479, point 3 stipulating an area within 200 m. measuring from the building construction control line as per map attached to the Act effective as the Buildings Control Act B.E. 2479 in the locale of Banglamung sub-district, Naklua sub-district and Nongprue sub-district, Banglamung district, Chonburi province B.E.2521 on the seafront side a building having the height above 14 m. may not be erected. The alignment of the buildings construction control pursuant to the Ministerial Regulations Issue 9, there had been an alteration to the plan attached to the Act stipulating the alignment of the building construction control line measuring seaward from the shoreline at the median sea level MSL a further 100 m. as the starting point of the alignment of the building construction control area. When there had been an extension of the alignment of the building construction control area stipulating the area within 200 m., measuring from the building construction control line was an area where a building having the height above 14 m. from road level may not be erected, according to the map attached to the Act the seashore where the median level of the sea was thus the same alignment with the Ministerial Regulations Issue 8. Therefore the alignment of the building construction control line then was extended seaward for 100 m. from the seashore at the mean sea level and on land the stipulated alignment was the original 100 m. as per the Ministerial Regulations Issue 8. If stipulated within 200 m. from the building control line as the end of the improvement to building zone the alignment forbidding construction, land side, as per Ministerial Regulations Issue 8 and Ministerial Regulations Issue 9 are then the same alignment.

4. The case of Rim View Talay Jomtien Condominium (1999) Co., Ltd. had submitted a letter dated 27th August 2005 for Pattaya City Hall to inspect the 100 m distance from the median sea level for Title Deed 104646, Nongprue sub-district, Banglamung district, Chonburi province. Pattaya City Hall had entrusted Mr. Chavalit Jariyabanjong in the position of Traffic Researcher 6 (Vor) to determine the distance of 100 m. from the alignment of the sea shore at median sea level holding the base marker in the area of the Meteorological Station, Khao Thappraya which the Navy had transferred the level value from Koh Lak in Prachuab Kiri Khan province. Pattaya City had therefore used the said basic level to find the mean level of the sea for Title Deed No. 104646, Nongprue sub-district, Banglamung district, Chonburi province of View Talay Jomtien Condominium (1999) Co., Ltd. (as per document attached No. 2).
5. The legal section has found the definition of mean sea level from the forestry technical survey, forestry engineering branch, forestry faculty, Kasetsart University who stated that the mean sea level was the average of the highest and the lowest tide levels of the sea. This mean level is considered international but it did not mean that the mean sea level was the same all over the world. The difference on mean sea level in America between Pacific ocean and Atlantic ocean differed about 1 m. (as per attached document No. 3)

Signed ………………………. Statement maker
(Mr. Niran Wattanasartsathorn)
Mayor Pattaya City


This explanation I, Miss Benjawan Chinnapat, lawyer 4 , Pattaya City was the arranger and typist.



Signed…………………………. arranger/ typist
(Miss Benjawan Chinnapat)
Lawyer 4


Garuda
Royal Insignia
Ref: Chor. Bor 52303/5548 Pattaya City Hall
North Pattaya Road
Banglamung,
Chonburi 20260

9th September 2005

Re: Please advise the 100 m distance from the median sea level

To: Mr. Kriengkrai Panichphakdi

In reference to: Letter from View Talay Jomtien Condominium (1999) Co., Ltd dated 27th August 2005

Enclosure: Copy of Title Deed 104646, 1 copy

In response to the request from View Talay Jomtien Condominium (1999) Co., Ltd., represented by Mr. Kriengkrai Phanichphakdi, Director, owner of Title Deed No. 104646, Nongprue sub-district, Banglamung district, Chonburi province to investigate the distance of 100 m. from the median sea level, Pattaya City has investigated and stipulated the distance of 100 m. from the median sea level as per detail attached.

Please be advised accordingly.


Yours sincerely,


Mr. Niran Wattanasartsathorn
Mayor, Pattaya City

Buildings Control Section and City Planning Signed
Civil Office, Pattaya City Mr. Pornsakdi

4 comments:

Anonymous said...

Don't give up!!

Anonymous said...

spes ultima dea

Hans said...

Is Thailand ruled by law or bribes?
Are our properties safe or not?

Anonymous said...

I hope VT 7 get built....

This will benefit the Kingdom, or more importantly the Thai people.

More projects on Jomtien = more foreign capital invested = more rich foreigners buying holiday retreats in Thailand = more money on Thai hands = more welfare to the Thai people.

I hope to judges will rule in favor of the Kingdom, not in favor of Jomtien Complex.

Go View Talay 7!

Long Live The King!